PROJECT: West Seneca Waste Water Improvements Plant 5

Project Details:

General Contract

Completed – September 2023

Cost – $2.7 M

Modifications to an existing buried divergence structure. Installation of a new 48-inch ductile pipe with associated manholes and structures. Sewer and manhole rehabilitation. Installation of new permanent flowmeters and associated connections to an existing programmable logic controller.