PROJECT: Lockport Raw Watermain
Project Details:
Owner – City of Lockport
Contract Value – $6,500,000
Year – 2019
Scope – This project consists of the replacement of approximately 9,260 linear feet of existing 30-inch raw watermain piping and approximately 2,030 linear feet of existing 24-inch transmission main piping along existing rights-of-way and along Summit Street in the City of Lockport, New York. A portion of the existing watermain needed to be replaced in place but the watermain could not be taken out of service. As a result a 30” and 24” bypass watermain system needed to be installed to keep the watermain in service.