PROJECT: ECWA BC-003 48″ & 42″ Transmission Main Condition Assessment

Project Details:

Completed – May 2023

General Contract

Cost – $650 K

Installation of two 16-in taps on the discharge header at the Sturgeon Point WTP located in the Town of Evans, installation of a new valve vault on Auckland Avenue located in the Town of Orchard Park, and a new valve vault located at the Windom Pumping Station Site in the Town of Orchard Park to house PCCP tapping sleeves and valve assemblies, furnishing two 24-in blind flanges with companion spool pieces and 4-in gate valves, and installation of condition assessment tracking locations including a pothole and 8-in pipe or valve box.