May 18, 2017PROJECT: SNI-CIA – TIS / Newtown Waste Water Treatment Plant – Phase 1
Project Details:
Owner – Seneca Nation of Indians
Contract Value – $2.7 Million
Year – 2010 – 2011
Scope – Phase 1 infrastructure construction for a new waste water treatment plant located at the Cattaraugus Territory Administration area of the Seneca Nation of Indians including.
- General contractor for new vacuum pump station building including sanitary sewer vacuum collection and pump discharge system pipe and equipment
- New administration pump station, valve vault, 4” underground force main, connection to existing gravity sewers, electric and emergency generator back up system
- 3200 LF 12” underground effluent piping including manhole structures
- 4000 LF 6” underground force main piping
- 600 LF 6” water main to new WWTP location
- Site and building prep for new WWTP
- Reconstruction of approximately 1200 LF of asphalt roadway