BNIA Fuel Farm Pipe Supports
May 18, 2017

PROJECT:  Seneca Nation of Indians – Community Scale Wind Energy Development

Project Details:

Owner – Seneca Nation of Indians / Sustainable Energy Developments (SED)

Contract Value – $645,000

Year – 2016

Scope – As a team member of the Seneca Nation of Indians and Sustainable Energy Developments, Kandey was subcontracted to perform the following tasks required for the installation of a new Vensys 1.5 MW wind turbine

  • Site clearing, grading, access roads and staging areas for new wind turbine installation
  • Cast in place concrete wind turbine foundation placed at existing grade over Controlled Modulus Columns (CMC)
  • Placement of embankment materials over new turbine foundation to act as ballast
  • Excavation, backfill and concrete encasement of new electric duct bank
  • Cast in place switchgear pad
  • Restoration of disturbed lawn areas